1. Rather than using Triangular Distribution while doing Three Point Estimation, you choose to use Beta Distribution. Based on your analysis and understanding, you are confident that the project would be completed with a total cost of $108,000. You also estimate that a best case would be $90000, while a worst-case scenario would result in the costs incurred to shoot up to $138000. What would the Three Point Cost estimate be when using Beta Distribution?

Explanations:The question states that you should do Three Point Estimation using Beta Distribution. The formula for this estimation technique is 4a + b + c / 6, where a = Most Likely Estimate, b = Estimate based on Best-case scenario, and c = Estimate based on Worst-case scenario. So, the Three Point Estimate using Beta distribution is (4 *108000) + 90000 + 138000 / 6 = 660000/6 = $ 110000.

2. John is managing a project. The project is about three-fourths done when the site engineer reports that due to inherent complexities in a certain task, the deliverables would get delayed. This would involve additional analysis and then implementation. He requests that this new work, which was not envisioned earlier, be added to the scope and also the time required be added to the schedule. You and the site engineer have analyzed the impact of this change to cost and have written up a change request and requested approval from change control board. Just today, you have received approval from the change control board. What should be the immediate course of action?

Explanations:As the change has been approved, you should always update the baseline (in this case, the scope and schedule baseline) before implementing the change. This will ensure that you track performance against the new scope and schedule, and not against the old benchmarks.

3. You are in charge of managing a software development project that is related to simulations for driving racing cars. In one of your team meetings, it is revealed that a lot of issues have been reported in the air tunnel modelling module. On deeper analysis, it is found that many of the issues could have been prevented had a simple code review checklist been used. You prepare a code review checklist and ensure the code is reviewed per the checklist. This is a good example of:

Explanations:This question is meant to test your understanding of the difference between corrective action and preventive action. Defect repair might sound tempting, but it is only applicable for the issues found in the current delivery. This is also not about Quality Control, so that leaves you with only two options: Corrective or Preventive actions. Corrective actions are always preceded by nonconformity, while preventive actions are never preceded by nonconformity. In this case, nonconformity in the form of a lot of issues during Quality Assurance were reported. The root cause was identified to be the need of a standard checklist which was later used. Preventive action is always taken proactively. In the question stated there is no demonstration of any proactive steps taken and hence this is not an example of Preventive action.

4. You have replaced an earlier project manager in a project .The earlier project manager has left the organization and you are now responsible for the project. On reviewing the project management plan you are disturbed because a number of procurement contracts have been signed off and they all turn out to be Cost plus fixed fee types of contracts. Why are you worried?

Explanations:As a project manager, you indeed have a reason to be worried if your project has already been signed off on Cost Plus Fee type of contracts. In such contracts, you, the buyer, needs to pay the seller for all the costs and also an agreed percentage of the cost. As a result, there is no motivation on the seller to control the costs; in fact, it is in the interest of the seller to increase the costs. It is not necessary that all projects should always be T and M or Fixed Price. Option A is clearly wrong since all the risks are, in fact, with the buyer and not the seller.

5. Your team is in its second month of development. You are managing a software development project for a banking product. In one of the team meetings, a debate arises if defects found during Quality control need to undergo change control. Some team members are convinced that all defects should undergo change control, while the others are convinced that defects need not undergo change control. Which of the following statements are untrue?

Explanations:Defects to deliverables, corrective actions, and preventive actions need to undergo change control. So all the above statements are true except option B.

6. You are responsible for managing a project that deals with laying out a freeway connecting two major port cities. Progress on the project has been smooth, and you and your team are very confident on completing the project well within the stipulated timelines. On reviewing, you see that the project has also run below the budget, resulting in savings. You decide to add an extra feature of reflector strips on the road every mile. You do a quick calculation and are satisfied that neither budget nor schedule will slip. You feel that by adding these extra features you could also bag some future projects. This is an example of:

Explanations:This is an example of Gold Plating. Integrated change control deals with formally approving or rejecting changes before they are implemented, so it is not the correct answer. Fast tracking is a schedule compression technique, so it too is not the correct answer. While Scope Creep is related to change in scope, it is related to uncontrolled changes in product or projects scope and is often due to client interference. Gold plating is done intentionally or knowingly for some strategic purpose. Here, the manager believes that by adding the extra features, future projects could be bagged.

7. You are in charge of a project that deals with laying out a lavish 18-hole golf course. The project work is in progress. You also have a number of contractors working on the project. Being an experienced manager you know that communication is key to success of the project. You have identified 10 stakeholders with whom you need to communicate. Due to some internal and external organizational changes at the client's end, three new stakeholders have been added with whom you need to communicate. You also had to reduce one of the contractors with whom you were communicating. How many communication channels do you have now?

Explanations:Originally, you had 10 stakeholders to communicate with, so the number of communication channels was 10 * (10-1) /2 = 45. However, 3 new stakeholders got added, while 1 stakeholder got reduced. So, the total number of stakeholders = 10 + 3 -1 = 12 and hence the total number of communication channels is (12 * (12-1)) /2 = 66.

8. You are in charge of a project, and to ensure things go well, you have had monthly meetings with the stakeholders. The project is running on schedule and budget. You are in your fourth month of execution, but the stakeholder indicates dissatisfaction with the deliverables. Making changes in the deliverables would mean a delay in the schedule. What would have been the most important process that could have prevented this situation?

Explanations:The most important process that could have prevented this situation would have been Scope Planning. Project deliverables are defined during scope planning, so proper implementation of this process could have prevented this situation.

9. The project that you are in charge has been successfully completed. The last of the deliverables have been formally accepted by the client. You had several contractors with whom contracts were prepared. With the project done, you decide to communicate the completion details and closure of contracts. Which is the best form of communication?

Explanations:As this is related to a contract, it must be a formal written form of communication. Any other form of communication related to contracts is not acceptable.

10. Your company has bagged a number of government contracts dealing with setting up infrastructure. This includes setting up roads and bridges. This is a very big and prestigious project, so your company wants to ensure everything is planned well in advance. You are the project manager of this project. Considering its importance, you and your team come up with a list of risks. One of the subject matter experts indicates that during the months of July and August, the construction work of the bridge across the river would need to stop on account of past history of flooding of the river. You agree with the expert and plan the schedule accordingly. What strategy did you just apply?

Explanations:This is an example of Risk acceptance strategy as there is nothing you can do about situations not in your control. Exploit is meant for positive situations, while risk mitigation is where you have a strategy to either reduce the risk impact or probability. Neither is transfer correct as the question does not state that someone else will be responsible for handling the risk.

11. You are in the process of defining activities and have broken down the WBS into individual activities. You now uniquely tag each activity with a unique code. So, you have defined an ___ for each activity.

Explanations:The question states that you have decided to uniquely tag each identified activity, which is nothing but Activity Identifier. This is done during creation of the Activity List.

12. You are managing a project that has teams located in different parts of the world. While the advantage of colocation is beneficial, the team structure or locations cannot be changed. Being an experienced manager, you realize that lack of a proper communication channel can quickly lead to chaos. What would your choice of communication be?

Explanations:Considering cross-located teams and difference in cultures, the best choice of communication in this case would be formal and written.

13. You are developing strategies to effectively engage stakeholders throughout the project life cycle. What is process you are working on?

Explanations:Plan Stakeholder Engagement is the process to develop a strategy to effectively engage stakeholders throughout the project life cycle.

14. You head the engineering department in your company. Lately, you have observed that certain deliveries are missing the schedule. On closer scrutiny, you observe this to be occurring with a specific team member. You decide to discuss it out with the team member. Initially, the team member is reluctant to discuss but finally opens up and indicates that the cause of the delays is often different instructions coming in from you as well as the project manager. She indicates that at such times she is confused related to whose instructions to follow, thereby causing delays. What kind of an Organizational structure is this most likely to be?

Explanations:Here the team member is being expected to follow instructions from both the Project Manager and the Functional Manager. This is never the case in a Functional or Projectized organization where the lines of authority are clearly defined. A weak matrix organization is more like a Functional Organization where the project manager has almost no authority. The scenario explained above is typical of a balanced matrix organization where power resides equally distributed between the functional and project manager.

15. The release criteria include:

Explanations:The release criteria include both the timing of the release of team members and the method in which you will release them.

16. As a project manager, you have successfully delivered all project deliverables within stipulated timelines. Your senior management wants you to calculate the Cost of Quality. As a project Manager, what costs would you NOT consider while making this calculation?

Explanations:All of the above are correct, except option A since hiring costs have nothing to do with Cost of Quality. Prevention and Appraisal Costs are the expenditures during the project to avoid failures, while Internal and External Failure Costs are those incurred during and after the project because of failures.

17. Which of the following is part of the Manage Quality process?

Explanations:Quality audits are part of the Manage Quality process.

18. You are the project manager for a project. You are updating the WBS during Define Activities. This process is often called ________.

Explanations:Updating the WBS during Define Activities is often called Refinements. It occurs with riskier projects.

19. The Project Quality Management process must __________.

Explanations:Project Quality Management addresses both the management of the project and the product. It improves project management as well as the quality of the product. It ensures that the project will satisfy customer requirements.

20. You are a project manager of a company, and your project is currently in execution phase. The customer has requested you for additional work. This work will affect the budget but not the schedule of the project. What should you do next?

Explanations:Explaining the change procedure and asking to submit a request for change is the best choice.

21. You are the project manager and have decided to outsource a part of the project to a vendor. You have offered a bonus to the vendor if the work is completed in two months. This is an example of:

Explanations:This is an example of project incentive.

22. You and your team have just created a schedule network diagram. You have come up with the estimates and have defined the durations and subsequently have identified the Critical Path. You now decide to do a Backward Pass" through the Schedule Network Diagram. What would you be calculating?"

Explanations:Options C and D are incorrect as the Backward Pass is not used to calculate the duration. In fact, the critical path is calculated based on duration. Option A talks about Early Start and Early Finish, which are calculated using Forward Pass." Using "Backward Pass

23. Of the following types of contracts, which has the highest risk for the seller?

Explanations:The riskiest for the seller among the options stated is Firm Fixed Price Contract, FFP. It’s a Fixed price contract in which total costs are fixed. The scope of work is clearly defined and stated. Cost-reimbursable contracts are the least risky for the seller since the costs are not fixed and paid at actuals. Time and material have medium risk from the perspective of the buyer and seller and are typically used for smaller dollar amounts.

24. What is the best use of a Work Authorization System?

Explanations:It defines how work will be authorized and how work will be done at the right time and in the right sequence. Option B is not correct since who performs the work comes from the responsibility assignment matrix and neither is option C the right answer. Option D is related to monitoring and controlling work performance data, which is not covered by Work Authorization System.

25. You are in charge of a software project and you are almost 40% complete. The project stakeholders want a performance report to date. You had planned to use Earned Value Management methodology. You come up with the following numbers: EV = 100 AC = 300 PV = 150 BAC = 600. You and your team have faced numerous issues till now. However, you choose to ignore the current work performance and decide to go with what was originally planned. Based on this information, what would be the EAC for the project?

Explanations:It is stated that the issues experienced in the project were ignored, so the past performance is not considered and the planned values are considered. So, the formula: EAC = AC + (BAC - EV) = 300 + (600 - 100) EAC = 800.

26. Your team has delivered phase one of a project to the client. Based on client feedback and issues found by the client, you decide to do some introspection to identify root causes so that the subsequent deliverables do not face the same issues. What techniques would you choose to apply?

Explanations:Quality Audits are meant to ascertain if the project activities conform to the policies and procedures, so it is not the correct answer. Activity Network diagrams are used for scheduling, while Process decision program charts are used to anticipate intermediate steps. The correct answer is Process Analysis, which is used to identify a problem and its cause and develop preventive actions.

27. Over lunch, you meet a colleague who is managing a large turnover project for setting up a chemical plant. Your colleague is worried because the client is being unreasonable and asking for changes that will have a severe impact on the scope schedule and cost. The client is also not ready to absorb the additional impact on schedule and cost. She seeks your advice. What should she do?

Explanations:Why is the client being unreasonable? Why does the client want to make these changes? Obviously, your colleague is in a tough situation. However tough the problem is, a project manager must not act impulsively by seeking legal action or refuse or immediately start making the changes. When faced with a problem, a project manager should first try and find the root cause and not react. So, in this case, the best advice for your colleague would be to set up a discussion with the client and try to understand the needs of the client.

28. You are managing a project to set up a brand new play area for the community. You and your team have been working as per plan and things are moving smoothly. Suddenly, one of the stakeholders indicates that the play area must also include a sand pit. This was not originally planned for, so you analyze the impact on the cost, schedule, and scope. You then submit the change request to the Change control board for their approval .You have immediately received an approval. What should your next step be?

Explanations:Once you have created the change request and submitted for approval, you don’t need to set up a separate meeting with the change control board unless asked for. Work performance reports will be shared as per agreed frequency. However, this is irrelevant to the question. You might be tempted to jump in and start work immediately, but first, the impacted baselines should be updated. In this case, all the three baselines have to be updated. This is necessary to ensure that performance information is tracked against the new baselines and not the old ones.

29. As a project manager, you are expected to calculate the cost of Poor Quality. The project work is in progress. What costs would you consider?

Explanations:Cost of Hiring has nothing to do with cost of Poor Quality, so it is not the correct answer. Cost of Poor Quality is just another term for Failure Costs. Failure Cost is generally categorized into External and Internal Failure costs, so option D is correct. Prevention and Appraisal costs are costs of conformance, which are the costs incurred to avoid failures. Hence, these are not considered cost of Poor Quality.

30. You are in charge of building a bridge across a river. All the initial groundwork and structural designs have been completed and work is in progress. You know that the next two months will be particularly critical involving some critical activities such as Arc welding of stiffener plates. You know your company employs welders who specialize in this kind of work. However, you are apprehensive about their availability for the next two months. What should you refer to first to find if these welders are available for the next two months?

Explanations:The correct answer is Resource Calendars. These provide information regarding availability of resources and also the duration of their availability. So, referring to these documents would be the first course of action.

31. You and a group of managers conduct a weekly meeting for sharing information and project management best practices. Joe who is a colleague of yours explains the need for correctly identifying all the project stakeholders. He explains that in his current project he has made use of Stakeholders Engagement Assessment Matrix. Many of the other colleagues are not quite aware of the need and usage of this matrix. Which of the following is the best choice?

Explanations:As the name suggests, Stakeholders Engagement Assessment Matrix is used to identify the current engagement level of project stakeholders. It can also be used to indicate the desired level of engagement. Through this analytical process, gaps in engagement levels can be identified and action plans and communication plans can be generated to bridge these gaps. The Stakeholder Engagement Assessment Matrix does not list stakeholders depending on their engagement level, so options C and D are clearly wrong. While you might be tempted to choose option B since you do list down all the stakeholders in a matrix in the document, the better and more qualified answer is Option A. Here, along with the complete list of stakeholders, you also indicate their current and desired engagement level.

32. Your company policy allows you to gift customers within certain limit. By mistake, you have given a gift to the customer's representative that is beyond the limit mentioned in your company policy. What should you do?

Explanations:The best option is to contact your company's senior management and ask for assistance.

33. Earned Value Analysis is used to measure performance based on a few parameters. Identify them.

Explanations:Earned Value Analysis is used to measure performance based on Scope, Schedule, and Cost.

34. Which of the following statements is not true regarding Scope Verification?

Explanations:All the options except Option D are true regarding scope verification. This process can also be done at the end of each project phase in the project lifecycle. So, the correct answer is option D since scope verification has nothing to do with schedule variance.

35. What is the purpose of a fishbone diagram?

Explanations:A fishbone diagram is used to illustrate how various factors might be linked to potential problems or effects.

36. Which of the following best describes Vroom's Expectancy theory?

Explanations:Vroom's Expectancy theory is based on the idea that people believe there are relationships between the effort they put in at work, the performance reviews/ratings they are credited for the effort, and the rewards they receive from their effort and performance review ratings. So, people will be motivated if they believe that hard work and effort will lead to good performance reviews and good performance reviews will lead to desired rewards. This theory consists of three key elements: Expectancy - Perception of an employee of how much and what amount of effort will lead to a desirable performance rating. Instrumentality - Perception or expectation that a good performance rating would translate into a hefty salary hike. Valence - Preference of an employee for a certain reward. Option B is clearly unrelated to this theory, so it is not the correct answer. Option C is related to Herzberg’s Hygiene theory, so it too is not the correct answer. Option D is about Maslow’s Theory of Hierarchical needs, so it's not the correct answer.

37. You are managing a project that your company won after making a bid. The clients have negotiated long and hard and have driven a hard bargain. The project is scheduled to span over eight months, and you are in your fifth month of execution. You are extremely worried since you have about four more months of work remaining and the project is at the Point of total assumption." What does this mean?"

Explanations:The point of total assumption (PTA) is a point where cost overruns will cause a dollar for dollar decrease in profit for the seller. Hence, any subsequent cost will have to be borne by your company.

38. You are managing a project which involves building software for the aeronautical domain. The nature of the work is complex and needs a lot of research. During Quality assurance, both the development team and testing team suggest that the quality assurance process be changed to include White Box testing and not just rely on Black Box testing. The teams want to make this shift in approach as they believe this would lead to better quality of deliverables. What is the best course of action?

Explanations:This is a question meant to test your understanding of change management. Any change, however small or big, should always be first analyzed for its impact on the constraints—scope, cost, and schedule—and then submitted to change control for approval. Changes without formal approval should not be implemented.

39. The Scope Baseline consists of _____.

Explanations:This is the only correct answer.

40. You are the project manager and decided to outsource a part of the project to a vendor. The vendor discovered some issues that impact the cost and schedule of its work. How does the vendor update the agreement?

Explanations:A contract addendum needs to be signed by your company and the vendor.

41. As a manager on a project, you have to ensure that the project delivers within the scheduled timelines with minimal rework and customer delight. For some time now, the project work is proceeding smoothly with a CPI and SPI a perfect 1. One of your team members approaches you and indicates the possible need of a long vacation on personal grounds, and this could possibly occur two months from now. You look up the schedule and finds that this team member is scheduled to execute activities that are on the critical path and the team member's absence in two months’ time would cause a delay in schedule. You decide to take some action and reschedule task allocation to ensure that this team member is not planned to work on any of the critical path activities. What did you just do?

Explanations:You have avoided the risk. By interchanging the tasks, you have ensured that the resource who could go on a long vacation does not work on critical path activities. There is no question of exploiting the risk as this is not a positive risk. This is not a case of risk mitigation since you have neither created a backup plan nor come up with an alternate strategy.

42. You are in the process of executing a project that deals with laying out electrical cables connecting two cities. You have been reporting progress on a monthly basis. This month, due to unplanned vacations, many of the staff have not turned up at work. This has caused a delay in the schedule. You decide to check if the schedule variance is within the allowable threshold. What document should you refer to?

Explanations:The acceptable schedule variances are defined in the Schedule Management Plan.

43. Which of the following activities is not performed as a part of Project Closure?

Explanations:All the options except verifying scope" are performed during project closure. Ensuring deliverables meet contract requirements and formal acceptance are key activities of project closure. Capturing lessons learned is also a very important activity performed during project closure. However

44. Which of the following types of contracts has the highest risk for the buyer?

Explanations:The riskiest for the buyer among the options stated above is Cost plus fixed fee. It’s a cost-reimbursable type of contract in which total costs are unknown, so there is an element of risk involved as the total scope of work is not clear. Time and material have medium risk from the perspective of the buyer and are typically used for smaller dollar amounts. Of the options, the fixed price options are the least risky for the buyer since the cost will not change no matter what for the buyer.

45. You are in charge of building a shopping portal. You are fairly confident as you have a team experienced in doing such work. As per the agreement at the end of the first month, you organize a demonstration of the software. You invite the sponsor and key stakeholders. Later, the sponsor informs you that she is not very happy with the progress, indicating that one of the clients who would be using this software is not satisfied as her needs are not being met. Satisfying this client's needs would mean some radical changes with an impact on both cost and schedule. What could be the root cause of this issue?

Explanations:The correct answer in this case is improper stakeholder analysis - Option D. While options A, B, and C could be true, the question gives no indication of these being the case. The question does mention about an important client whose expectations were not met. Stakeholder analysis deals with identifying all the stakeholders, their needs and expectations, and their influence. In this case, the client's needs are not being met, which indicates that stakeholder analysis and identification were not done correctly.

46. Top-down estimating is also called _______ estimating.

Explanations:Top-down estimating is also called analogous estimating.

47. The ____ is the international organization that controls the standards for quality.

Explanations:The ISO is the international organization that controls the standards for quality.

48. Your company has won a large project—administering funds for one of the fund houses. The project work has been going on smoothly and the customer has been praising the work done so far. The client has planned a visit the next month to go over the plans for the next phase of the project as well as to meet with the project team. Your senior management realizes that this client could potentially need additional capabilities in the derivatives segment. Your company has a strong exposure to this segment having executed numerous such projects. Your senior manager also invites key managers from the derivatives segment to showcase the organization's abilities in the derivatives vertical. What is this an example of?

Explanations:This is an example of exploiting the risk. The client is happy with the work progress, and there might also be an opportunity that the client could be interested in the derivatives segment. This opportunity could lead to more business. By inviting key managers from the derivatives segment, you are enhancing the possibility of generating additional revenue. Hence, this is an example of exploiting the risk. Note that this is a positive risk.

49. Project Team has created sub-plans for each activity in the project plan. These plans are called:

Explanations:These plans are called management plans.

50. You are responsible for the complete makeover of a shopping mall, which involves civil work and painting. After going through the details, you have come up with the cost estimates which have been approved to arrive at the cost baseline. Work is now in progress, and you and senior management are happy with the work. Suddenly, you realize the ceiling repair work was not factored in the estimates though it was very much a part of the scope. You decide to make use of Contingency reserves, but your senior manager advises you to make use of the Management reserve. What is the correct action?

Explanations:Management reserve is meant for unknown unknowns and is part of the scope of the project. The question clearly states that the work is in scope. Contingency reserves are for known unknowns, which is not the case here. The correct answer is Management Reserve.

51. You are in your third month of project execution, which is expected to continue for a duration of 14 calendar months. Your sponsor has asked for a performance report. You decide to create an “S curve”. Based on the S curve, you report your Actual Cost, which is more than the Earned Value. Also, the Planned Value is greater than the Earned Value. What would be the interpretation of this data?

Explanations:This is because both SPI and CPI are less than 1.

52. You have been asked to provide Cost estimates for a project which would be responsible for the complete electrical installation in warehouses. As a project manager, you have had past experience in similar projects in your previous organization. The organization you have joined also has recently done a similar project. There is an urgency in providing the estimate as mandated by executive management. What estimation technique would you adopt?

Explanations:Analogous estimating relies on previous similar projects as the basis of estimation. So, it relies on historical information. This technique is used when there is limited amount of detailed information like during early phases of the project. It is less costly and less time-consuming. As time is a constraint as stated in the question, this is the best choice.

53. You are a project manager managing a project that has not been making good progress. Certain issues like a flash flood have significantly delayed the laying out of the plinth for the shopping complex. There have been a lot of escalations from key stakeholders, and executive management is pressing for getting the project on track. In a review meeting, your lead architect, sensing the urgency, suggests a change that could significantly reduce the schedule. She is very confident that the suggested change will work to get things on track. As a project manager, what is the best course of action?

Explanations:No changes should be made without a formal approval, so option A is clearly wrong. Rejecting ideas without doing a thorough analysis of the impact is also not the correct approach. Now the option of creating a change request and submitting it for approval sounds like the right option. However, the better approach is to always do an analysis of the impact on scope, time, and cost and then submit the change request. So while option C is correct, the better option is D.

54. You are in charge of managing a software development project which is related to simulations for driving racing cars. In one of your team meetings, it has been revealed that a lot of issues have been reported in the air tunnel modelling module. On deeper analysis, it is found that many of the issues could have been prevented had a simple code review checklist been used. You decide to mandate usage of the code review checklist for all subsequent deliveries to ensure other deliveries are less issue prone. This is a good example of :

Explanations:This question is meant to test your understanding of the difference between corrective action and preventive action. Defect repair might sound tempting, but it is only applicable for the issues found for the current delivery. Here, the question also states some additional steps being mandated (code review for all subsequent deliveries). This is also not about Quality Control, so that leaves us with only two options - Corrective or Preventive actions. Corrective actions are always preceded by nonconformity, while preventive action is never preceded by nonconformity. In this case, nonconformity in the form of a lot of issues during Quality Assurance was reported. The root cause was identified to be the need of a standard checklist which was then used. This would have been a case of Corrective action had no other actions been taken other than usage of the code review checklist for the current delivery. In addition, a decision was taken to use the checklist for all subsequent deliveries to ensure the same issues did not occur. Preventive action is always taken proactively. Here, mandating usage of code review checklist for other deliveries is a demonstration of proactive steps taken. Hence, this is an example of Preventive action.

55. You are in charge of constructing a high-rise residential building. After creating a Network diagram, you have identified the Critical Path. Work has started, but suddenly due to inclement weather, plinth work has got delayed. This plinth work activity was on the critical path. As a manager driving this project, would you be worried and why?

Explanations:If activities on the critical path are delayed, it can lead to a delay in the entire Project. Hence, options A and B are incorrect. Option D is a very subjective answer, and nowhere does the problem state how the stakeholders would take the news. So, the best answer is option C.

56. You know that the success of your project will be determined by how well you manage risks. You know that identifying risks upfront can help you be better prepared with risk response strategies. You discuss and consult with other project managers in the company. One manager suggests usage of SWOT to identify risks. What would you do next as a part of this technique?

Explanations:SWOT involves identification of the strengths and weaknesses of the organization. This technique then identifies the threats due to organization's weakness as well as opportunities due to the organization's strengths. So, option D is the correct answer. The other three options are also risk identification techniques, but the question is specific to SWOT.

57. You have been assigned to a project that deals with developing a software product for the BFSI domain. You and your team are building the schedule network diagram. While sequencing activities, one of the team members, who is an Architect, indicates that rather than interacting with the database on every activity, you should introduce an activity which would cache the data. The team member argues that this will improve performance and hence this activity should be introduced in the sequence prior to the other activities that deal with database interaction. What kind of a dependency is this?

Explanations:Discretionary Dependency is also known as Soft Logic or Preferred Logic or Preferential Logic. Note that this is not a mandatory dependency as it is not a Must Have" but more a "Should have." Discretionary dependency decisions are usually based on best practices and business knowledge. In this case

58. You and your team are in the process of creating WBS and WBS Dictionary. What would be the best choice of attributes in a WBS Dictionary?

Explanations:Options A, B, and C each provide great details of what a WBS Dictionary should contain. So, they all seem like the right choices. However, the question asks about the BEST choice of attributes in a WBS Dictionary, which is provided in Option D. Note that the WBS and WBS Dictionary are corelated by WBS Name and Work Package ID

59. Which of the following statements is NOT true regarding change log?

Explanations:The change log is used to log all change requests—approved and rejected changes. Along with the changes, their impact on cost, time, and risk details are also documented. So, option A is not true regarding change logs and hence is the correct answer.

60. S Curve depicts a relationship between:

Explanations:S curve shows a relationship between Actual Cost, Planned Value, and Earned Value.

61. Which of the following statements is false regarding Risk Management?

Explanations:All of the statements are true except the statement regarding Quantitative Risk Analysis. Quantitative Risk analysis does not deal with prioritizing risks. The prioritization occurs in the Qualitative Risk Analysis process. Quantitative Risk Analysis deals with assigning numeric values to risks.

62. Which of the following statements is not true regarding Contracts?

Explanations:This question tests your knowledge of contracts and procurement. At the onset, all the answers seem to be correct with respect to contracts. A contract is legally binding in nature; it’s an agreement between the seller providing some service or product and the buyer compensating the seller. Some of the risks can indeed be transferred to the seller through terms and conditions. Due to the legal nature, contracts are subject to an intensive approval process, much more intense than other plans. Hence in the context of the question, option D is the right answer.

63. You are in charge of a project for the electrical layout of a five-star hotel. You see this as a very simple project as you and your team have a lot of experience executing similar projects. As a result, your organization has a wealth of Organizational Process assets. You have worked out the exact details of the work involved and have a very detailed WBS with granular-level activities defined. You decide to employ the services of a contractor for laying out of the cable trays. What kind of a contract would be the best choice?

Explanations:When as a buyer you are clear of the scope and statement of work, the contract choice should be Fixed-price. In this type of contract, if scope is clearly defined, then almost all the risk lies with the seller. Here, the buyer is smug with the confidence of having had experience in executing similar projects in the past and has also broken down WBS into detailed activities. So, scope is clear and the correct answer is option B.

64. Which hierarchical chart shows resources?

Explanations:The Resource Breakdown Structure shows various resources, both human and mechanical, needed for the project.

65. Your company has won a project to build a school playground with specific toys and a sandpit. The school has mandated that the project be completed before the school starts after holidays. You review the plan and see that the estimated completion date is nearly a month after the desired completion date. As resources are sparse, you do not have the option to add additional resources. However, you see that the sand pit work can start in parallel with the play kits being installed. Your analysis tells you that by performing these activities in parallel, the project would meet its schedule. This is an example of:

Explanations:Crashing deals with adding additional resources, and is not an option here. Fast Tracking is a schedule compression technique by performing activities in parallel if they can be overlapped. Note that Fast Tracking may result in increased risk and rework.

66. You are in charge of a project to build a bridge across a river. You are midway through the project. However, due to changes in environmental laws, the project can no longer proceed and would need to be terminated. Executive management has asked you to document the level of work completed for the project. In which of the following processes would this be done?

Explanations:Scope verification is performed not only while a project is being executed but it is also performed when a project is terminated. It is used to determine the level of completion.

67. You have asked your team members to provide estimates of tasks. You see that a specific team member has provided estimates on the higher side. You discuss the matter with the team member, and get a reply that as the team member did not have an idea of how long it would take, the team member had guessed the estimate and then to be on the safer side simply doubled it. What is this known as?

Explanations:Pad is adding time as a buffer to project estimate. As the team member was uncertain of what it would take and, as stated, to be on the safer side she simply doubled the estimate. Padding is a sign of poor Project Management.

68. You are in the process of making cost estimates for a project. However, detailed requirements are not yet available. A similar project was executed by your company, and you decide to use the past project's historical data to come up with your estimates. This is called:

Explanations:The correct answer is Analogous estimating. It relies on past or historical data of similar nature. As the project is at an early state, where the detailed requirements are not yet available, this is the best technique suited to come to an early estimate, though it may not be very accurate.

69. You are the project manager for a large Project. You are currently busy with approximating the number of work periods required to complete individual activities with estimated resources. Which of the following inputs do you need for this?

Explanations:The process is Estimate Activity Durations. And for this process all the options mentioned are used as inputs

70. You and your team are planning out the work to be done. You break up the work into discrete work packages. To ensure that each work package has all the necessary details, you and your team decide to write down detailed information for each work package such as Statement of work, details of the work package, and who will be the responsible individual for the work package. Where would you store this information?

Explanations:This is where this information is stored.

71. You are the project manager of a software project. You have just analyzed activity sequences, durations, resource requirements, and schedule constraints and created project schedule. To which process does the above tasks belong?

Explanations:Analyzing activity sequences, durations, resource requirements, and schedule constraints and creating project schedule belong to Develop Schedule process.

72. You know that the success of your project will be determined by how well you manage risks. You know that identifying risks upfront can help you be better prepared with risk response strategies. So, you decide to identify risks by taking help of experts. You have identified some experts, and rather than calling them to your office, you send them questionnaires. You promise them complete anonymity so that they give unhindered responses. What information gathering technique are you adopting?

Explanations:All the four options listed above are information gathering techniques, but the correct answer is Delphi Technique. This is a form of information gathering technique where inputs from experts is solicited anonymously without gathering them together.

73. Which of the following options best describes Achievement Theory of Motivation?

Explanations:Option A and Option D are related to Expectancy theory; Option B is related to Theory X style of management. So, these options are not the correct answers. Option C is the correct answer. The Achievement Theory of Motivation states there are three types of motivational needs: need for achievement, need for authority and power, and need for affiliation. As per this theory, a strong affiliation motivation" undermines a manager's objectivity because of his need to be liked

74. The key benefits of ____________ process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and the environment changes.

Explanations:The key benefits of Monitor Stakeholder Engagement process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and the environment changes.

75. You are managing a project for constructing a bridge over a river. All the risks have been identified and the design phase is just completed. The team is in its second week of construction. One of the subject matter experts reports that there is a possibility of the monsoons to be heavier this year. She points out that the load-bearing plates earlier designed may have to be redesigned considering the additional water pressure expected because of additional rain water. What would be your best immediate course of action?

Explanations:The question is asking about the best immediate course of action. The first course of action should be to add this risk in the Risk register. The possible impact and risk probability should also be added. No other action should be performed prior to this. So, scheduling an emergency meeting, which might sound as the first thing to do, is not correct and neither is making any change to the design. Writing up a change request will only come after the risk is documented and its probability and impact accessed. So, the first course of action should be to update the Risk register.

76. You are managing a project responsible for doing plantation on a large reserve land. You have created the schedule network diagram and have identified two paths. Path 1 consists of two activities of a duration of 2 and 5 weeks, respectively. Path 2 consists of 3 activities with durations of 1, 3, and 3 weeks, respectively. Which of the two paths is the Critical Path?

Explanations:The duration of both the paths is 7 weeks. Remember that the path with the longest duration is the critical path and you can have more than one Critical Path.

77. What is the role of the Project Manager in Procurement?

Explanations:The project manager must ensure all of the above in Procurement. Many times the project manager works with the contract manager. An important point is that the Project Manager must be assigned before the contract is signed.

78. As a manager in an organization that believes in the Theory X style of management, which of the following do you think describes correctly the assumptions of this theory?

Explanations:Theory X assumes employees cannot be trusted and will only work if rewarded or under threat and coercion. This theory does not consider employees to work on their own. So, the correct option is A. The other options consider an employee to be self-motivated and self-starter, which is not what Theory X is based on.

79. You have recently joined an organization's project management office. After reviewing the organizational assets, you realize that project managers have not routinely documented lessons learned for their projects. There are a few projects that are about to start. You decide to call up a meeting of all the project managers and explain the need of Lessons Learned. In order to get a buy-in from your managers, what would you focus on as the best use of this document?

Explanations:Note that the question states that new projects are about to start and past lessons learned of projects could have served as good inputs for the other projects. Not having lessons learned handicaps the managers.

80. Your project is in a critical phase. You notice one of the team members comes in late to office and leaves early. This is clearly impacting delivery. You decide to discuss the details with the concerned team member to better understand the details. On discussion, you find no specific reasons, so you explain the necessity and criticality of the project, expecting the team member to improve. However, next week, your lead engineer reports about inadequate time being spent by the same person in office. What would be the best choice of communication in this case?

Explanations:In this case, you have already tried out the option of discussing with the team member once, which is an example of informal verbal. Clearly, that has not worked, so it calls for a more strict reprimand. Hence, the correct form of communication would be a formal written communication.

81. Decomposition is best described as:

Explanations:Decomposition deals with breaking down deliverables into small discrete work packages that can be planned better. It also helps prevent work from slipping through the cracks and gives the project team a better picture of the work involved.

82. As a part of the Executive Management team, you have a number of project managers reporting to you. One of the project managers has reported the data for their project that has got you worried regarding the health of the project. EV = $ 300000, PV = $ 550000, AC = $ 200000. You are worried since, as per your calculations, the project is behind schedule. However, the Project Manager disagrees and feels the project is ahead of schedule. What is the correct interpretation of the data?

Explanations:SPI = EV / PV = 300000/550000 = less than 1. An SPI less than 1 indicates the project is behind schedule.

83. Identify the basic quality tools to facilitate, measure, and control quality

Explanations:As per PMBOK® Guide - Sixth Edition, Pareto chart is not included as a tool under control quality process.

84. You have scheduled regular weekly team meetings with project team members. Things have been going according to plan and there have been no variances till date with respect to the work performance baselines. A site engineer reports that he had to perform a couple of corrective actions, but they were not logged. As a Project Manager, what should you do?

Explanations:All changes, including corrective actions, preventive actions, and defect repair, must undergo change control prior to the change being made. It is also necessary to document the corrective and preventive actions taken in historical data as this can serve as a good input for subsequent projects. Reprimanding the team member and allowing uncontrolled changes to happen are a recipe for disaster in project management.

85. You are negotiating with a contractor for additional staff augmentation—a number of software developers and a few testers. As a buyer, you don’t quite have the exact statement of work ready. What kind of contract is MOST appropriate for this kind of work?

Explanations:As the nature of work is not quite clear and this deals with contracting additional staff, the best choice of contract is T and M. Fixed price contracts are applicable where scope of work is quite clear, which is not the case here. Choosing a Cost-reimbursable contract makes no sense since the unit rate of staff can be determined and agreed between you and the seller. So, the best option is T and M.

86. A process with lack of consistency and predictability is called:

Explanations:A process with lack of consistency and predictability is called out of control.

87. The _________ details the different tasks for members in the project.

Explanations:Responsibility Assignment Matrix (RAM) details the different tasks for the members in the project.

88. ISO Stands for __________.

Explanations:ISO Stands for International Organization for Standardization.

89. Your project activity float is negative 10. What is your course of action?

Explanations:Negative activity float indicates your project is behind schedule. Adding more resource is the best option.

90. The purpose of a quality audit is to:

Explanations:The purpose of a quality audit is to identify inefficient and ineffective policies.

91. Which of the following statements is not true regarding the Scope Management Plan?

Explanations:All the options except Option A are true regarding the Scope Management plan. The Scope Management Plan is part of the Project Management Plan.

92. You are the project manager of a project and have added some dummy activities to correctly show all logical relationships. Which network diagramming method have you used?

Explanations:ADM (Arrow Diagramming Method) uses dummy activities to correctly show all logical relationships. Arrow Diagramming Method (ADM) uses arrows as activities, and nodes are used to connect and show dependencies. The Precedence Diagramming Method (PDM) uses boxes or nodes as activities and arrows as dependencies between the nodes.

93. You are in charge of a painting project for a high-rise building. As part of the planning, you need to take a decision of buy vs. lease some stilt ladders needed on site. The cost of the ladder is $1000 and a daily cost of $4, while the daily lease cost is $12. If you were to lease the ladder, what should be the duration to ensure your decision is correct?

Explanations:Let’s assume the duration to be X days. 12 * X = 1000 + 4 * X, 8X = 1000, X = 125. This means that if the ladder is used for any duration equal or greater than 125 days, it is economical to purchase rather than lease. So, in other words, to lease the duration should be equal to or less than 125 days.

94. In which of the following situations is network diagram better than bar chart?

Explanations:Network diagram is best to show Interdependencies between activities.

95. Your company has been tasked with providing estimates for a road construction project. You have data available related to costs per square feet. You now need to provide an estimate of the cost of the project based on this data. What estimation technique is most applicable in this scenario?

Explanations:Parametric Estimation is most applicable in this scenario as the cost per unit is readily available. Parametric estimation uses the relationship between variables to determine cost or duration. It calculates the cost or duration of the unit and also determines the number of units required. This helps in calculating the cost/duration of the project.

96. A data point in a control chart that requires investigation is called:

Explanations:A data point in a control chart that requires investigation is called a special cause.

97. A Heuristic is best described as:

Explanations:A Heuristic is a thumb rule. An example is cost per square feet.

98. You have successfully completed a project. You have now been assigned a project which is midway in its execution. You have had to take up this project due to non-availability of the current project manager. This is a complex project involving multiple contractors and teams at various geographical locations. You decide to look up the requirements of the types of reports and frequency of sending them. Where would you find this information?

Explanations:The correct answer is Communication Management Plan. This Plan provides information such as frequency of communication, type of communication, and who is responsible for communication.

99. You are managing a project, and to ensure things run smoothly, you have decided to provide project information periodically to all the stakeholders. You have decided that you would report against the baselines for scope, cost, and schedule. Which of the following would be the best choice?

Explanations:The best choice is Performance reporting with respect to the triple constraints - Scope, Schedule, and Cost. Forecasts are future projections and risk register deals with risks, which are not the right options. While status reports could be an option, the best answer is Performance reporting.

100. You have replaced a project manager on a project that is already in the execution phase. The project is behind schedule, and you have been specifically brought in to ensure the project meets its schedule. You decide to review the schedule network diagram created by the earlier project manager and realize that the project is 3 weeks behind schedule. After reviewing the activities and the network diagram, you decide to Crash the schedule. This means you:

Explanations:Crashing is a technique used to shorten the schedule by adding resources. Options A and D are clearly not correct, and Option C is an example of Fast Tracking.

101. Which of the following best describes the assumptions made by Herzberg's Hygiene theory?

Explanations:According to Herzberg's Hygiene theory, certain factors termed Hygiene factors" exist. Their absence can lead to dissatisfaction. So

102. You are managing a software development project in the banking domain. Things have been proceeding as per plan, but with the economic meltdown, the client has had to abruptly shut down the project due to lack of funds to source the projects any longer. As a Project manager, what is the next thing to do?

Explanations:Project closure procedures must be followed. They must be followed irrespective of whether the project was successfully completed or if it was terminated. We always follow closure procedures. So in this case, the Project Manager should choose option C.

103. Which of the following statements is true regarding Critical Path?

Explanations:Generally activities on Critical Path have Zero float. Critical Path is the one which has the longest duration. So, options B, C, and D are not correct. You can always have more than one Critical Path in a project.

104. Your company policy allows accepting gifts from customers within certain limit. Your customer is giving you a gift that is beyond the limit of your company policy. You have already given a gift that has similar value to the customer's representative . What should you do?

Explanations:Best option is to contact your company's senior management and ask for assistance.

105. You are responsible for a project with high risks particularly during the early phases. Your sponsor has asked for performance reports on a monthly basis. At the end of the first month, you report a CPI greater than 1 and also the SPI greater than 1. What would this mean?

Explanations:SPI greater than 1 indicates the project is ahead of schedule, while a value less than 1 indicates the project is behind schedule. CPI value greater than 1 indicates project is under budget, while a value less than 1 indicates the project is over budget.

106. You are the project manager of a software project. Your team member wants to make technical changes to an activity, which will add more time to that activity. What should you do?

Explanations:Check if the activity is on critical path" is the best option."

107. You have taken over a project from another project manager. The project is already in its third month of execution. You need to determine if the project is ahead of or behind schedule. What would be the best source of this information?

Explanations:Earned value analysis provides details of planned vs. actual values that help in determining the health of the project. Work performance data is the actual information that helps in measuring performance. Project management software helps track data, while Pareto chart is used in Quality Control.

108. Communication can be of the following forms except:

Explanations:Precise and vague are not forms of communication, while all others are.

109. You are the project manager of a project, and one of the functional managers wants to make a major scope change during the execution of the project. What should be your action?

Explanations:If there is scope change by a functional manager during the execution of the project, then the project manager sends the impact detail of the changes to functional manager.

110. As you have a lot of expertise in project management, many of your company's co-managers consult you for advice and inputs. One of your colleagues who is relatively inexperienced in managing projects wants to compare the project work and measure the deviations. Which document should he refer to? Choose the option that best answers the question.

Explanations:There are multiple options that seem correct; however, they are partially correct. The scope baseline and schedule baseline are not the only baselines against which project performance is measured, so options B and C are definitely not the best options. The project management plan contains details of all the baselines, but a more specific plan to refer to is the Performance Measurement Baseline. It contains details of the scope, schedule, and cost baseline, and it could also contain quality and technical parameters. While the project management plan includes the baselines, it is actually the Performance Measurement Baseline which is used for comparing performances, and the Performance Measurement Baseline is a part of the Project Management Plan.

111. As a manager on a project, you have to ensure that the project delivers within the scheduled timelines with minimal rework and customer delight. For some time now, the project work is proceeding smoothly with a CPI and SPI a perfect 1. One of your team members approaches you and indicates that she might possibly need a long vacation on personal grounds. She indicates this could possibly occur in two months from now. You look up the schedule and finds that this team member happens to be scheduled to execute activities that are on the critical path and her absence in two months’ time would cause a delay in schedule. You decide to take some action and ask the team member to start regular knowledge transfers to a couple of trainees. Though the trainees would be relatively inexperienced, they would more than make up for it with two people rather than one person to perform these tasks should this team member need to go on leave. What did you just do?

Explanations:You have mitigated the risk, where by asking for the trainees to be trained, you have created a Risk response strategy. Should this team member go on leave, the trainees would execute the task. So, you have not avoided the risk. Again, there is no question of exploiting the risk as this is not a positive risk. This is not a case of Risk transfer either, so the correct answer is Risk Mitigation.

112. You are a project manager of Software Product Company. After a person is hired, you come to know that many of this person's ideas were developed by a competitor company. Which of the following is the best action in this case?

Explanations:Unless the employee has signed the NDA with his previous organization, there is no obligation for him not to share knowledge that was gained while working for the competitor.

113. A product description of a project can help in creating procurement details. Which of the following best describes the product description?

Explanations:A product description defines the contracted work based on the requirements of the customer.

114. As a project manager of a project, you have just completed Schedule network diagram. Which of the following schedule management activities have you completed?

Explanations:Schedule network diagram is an output of Sequence Activities.

115. You are in the process of making a cost estimate for a large prestigious project. You decide to use the Three Point Estimation technique with Triangular Distribution. Based on your analysis and understanding, you are confident that the project would be completed with a total cost of $108,000. You also estimate that a best-case estimate would be $90000, while a worst-case scenario would result in the costs incurred to shoot up to $138000. What would the Three point Cost estimate be using Triangular Distribution?

Explanations:The question states the use of Three point estimate using triangular distribution. The formula for this estimation technique is a + b + c /3, where a = Most Likely estimate, b = Estimate based on analysis of the Best-case scenario, and c = Estimate based on analysis of the Worst-case scenario. So, the Three point estimate using Triangular distribution is 108000 + 90000 + 138000 / 3 = 336000/3 = $ 112000.

116. Midway through the project, as a Manager, you are performing Earned Value Methodology to report performance. Based on your calculations, you realize that the initial plan is no longer valid. However, you still need to provide an EAC. What is the best course of action?

Explanations:Option A is to be used if past CPI is expected to continue. Option B is to be used if future work is going to be performed at the planned rate. Option C is to be used if both CPI and SPI influence remaining work. Option D is to be used when the initial plan is no longer valid, which is the case here.

117. As a manager on a project, you have identified and created the WBS and WBS Dictionary. You also plan to ensure that each deliverable gets the approval of your stakeholders and sponsors. Which process are you planning to perform?

Explanations:Validate scope deals with validating what was delivered and what was required.

118. You have received a number of seller responses for contracting work related to setting up office cubicles. One of the bids received happens to be from a very good friend of yours. You know she has done good work in the past. What should be the best course of action?

Explanations:This is the only correct answer.

119. In order to determine the details of the work to be performed in work packages, which of the following can be used?

Explanations:WBS Dictionary provides details such as description of work to be done for each work package, any schedule milestones, and statement of work. It is also used to prevent scope creep.

120. You need to provide estimates for activities on the project. You and your team discuss and conclude that as detailed information is not yet available, the best option would be to use Parametric Estimates. Which of the following is used to create Parametric Estimates?

Explanations:You have mitigated the risk. By asking for the trainees to be trained, you have created a Risk response strategy. Should this team member go on leave, the trainees would execute the task. So, you have not avoided the risk. Again, there is no question of exploiting the risk as this is not a positive risk. This is not a case of Risk avoidance either, so the correct answer is Risk Mitigation.

121. Which of the following best describes the role of a project sponsor?

Explanations:The project sponsor is not responsible for managing the project nor the quality of deliverables; it is the role of the project manager. While the sponsor can aid in identifying key stakeholders, the key area a sponsor plays a part in is providing funding. The sponsor provides funding directly or indirectly and is responsible for approving or denying the budget. The project sponsor is also generally the one who approves the Project Charter, but that is not mentioned in the question.

122. You are a project manager for a project. While reviewing the cost estimates for the project, you notice that one of the cost estimates for an element in the WBS is 20% higher than the previous project for a very similar work. What should you do next?

Explanations:The best option is to ask the person responsible about the difference and create the most accurate estimate that is practical.

123. You are the sponsor of a project which has just kicked off. This is an ambitious project to build a top-of-the-line 18-hole golf course. Which of the following best describes your role as a sponsor?

Explanations:The main objective of the sponsor is to create and publish a formally approved project charter. While the sponsor can help assist in preventing and managing changes to the project, this is the project manager's job. Creating baselines and publishing work performance reports are also the job of the project manager.

124. As a project manager of a project, you have just completed Schedule network diagram. What should you do next in schedule management?

Explanations:Schedule network diagram is an output of Sequence Activities, NEXT process is Estimate Activity Resources.

125. The key difference between Work performance data and Work performance report is:

Explanations:Work performance data is converted to work performance information. This in turn is converted to work performance reports, which provide the staus in the form of electronic dashboard.

126. The purpose of a contract is to distribute a reasonable amount of ____________between the buyer and seller.

Explanations:A fair contract shares a reasonable amount of risk between the buyer and the seller.

127. A friend of yours approaches you seeking advice. She indicates she has offers from two organizations. Her role in one organization is that of a project Coordinator, while in the other organization, her role is that of a Project expediter. She is not quite clear of the difference between the two roles and seeks your advice. Which of the following statements is true?

Explanations:A project expediter has no authority or decision-making ability. A project coordinator has some amount of authority and some amount of decision-making ability.

128. If a person desires to excel in his tasks, as per Maslow's Hierarchy of Needs, what type of need is the person exhibiting?

Explanations:When a person desires to exceed or excel in her tasks, it is considered the highest level of need. The person now wants to realize her full potential, which is Self-actualization.

129. According to Theory Y style of management, which of the following is a correct assumption?

Explanations:Theory Y believes positively about employees, and only option D reflects a positive attitude and belief. Option A, B, and C are not the correct answer as they are the opposite of belief in employees. They indicate lack of trust in an employee, which is not a correct assumption in the Theory Y style of management.

130. Conformance to specifications document is a description of:

Explanations:Quality on a project means that you are conforming to a standard that is set before you start the project.

131. You are the project manager of a marketing project and need to purchase some equipment. The accounting department needs a unilateral contract from you. To which of the following is the Accounting department referring?

Explanations:A unilateral contract is simply a purchase order.

132. You are out for lunch with a fellow project manager. She is in charge of a project that deals with laying out electrical cables across two towns. As you understand the plan of the layout, you realize that the cabling would cover a neighborhood with a history of criminal problems. You advise your fellow team manager that it would be prudent to insure the copper cables through a theft insurance. You also advise her regarding which insurance companies would give her the best insurance covers against theft. Which risk response strategy did you just adopt?

Explanations:This is an example of Risk transfer where you have advised your fellow manager to insure against theft through insurance. Note that this does not eliminate the risk rather the risk is simply to be borne by the insurance company. It is also worthwhile to note that the transfer of negative risks comes with a premium to be paid to the party responsible for handling the risk. In this case the insurance company would need to be paid a premium for bearing this risk.

133. To Complete Performance Index is used to:

Explanations:TCPI is a measure of the ratio of the work remaining to the funds remaining.

134. You are managing a project, and based on risk identification, you feel very confident that the project should run smoothly. The next day the lead architect indicates a risk which was not envisioned. He indicates a 10% possibility of the risk occurring and the effort involved in choosing an alternate path worth 2000 USD. The side effect of alternate path implementation is that a lot of testing efforts would get reduced worth 4500 USD and the possibility being 30%. What would be the EMV?

Explanations:The correct answer is $1150. In the case of the rework effort, the EMV is -$200. The EMV of the side effect is $1350. So, the total EMV is $1150.

135. An estimate is required for a new project of an R&D nature, and it has been decided to create the estimates using WBS with an emphasis on accuracy of the estimates. Your project manager also indicates that sufficient time is being made available to provide the estimates. What would be the best estimation approach in this case?

Explanations:Parametric and Analogous are clearly not the right choices. Being a new project, you do not have any historical data to rely on. So, Analogous estimation is not an option. You also don’t have any data of costs per unit, so Parametric estimation is also not an option. Now between Top-down and Bottom-up, both these approaches use the WBS to come up with the estimates. With Top-down, we start with the high level and then drill down into the lower levels. Bottom-up estimates are more accurate compared with Top-down. Bottom-up is also a more expensive and time-consuming type of estimate. However, the question clearly indicates that time is not a concern. So, the correct answer is Bottom-up approach. Top-down approach is used only if we have enough historical information on the project, which is not true here.

136. Which of the following could not be provided with Activity Attributes?

Explanations:All the options are correct except option D. Activity attributes do not provide details of root causes of issues.

137. As a project manager, you understand the importance of identifying all relevant stakeholders, their interest and influence, and their needs and expectations. You have been assigned to handle a large construction project. You decide to do a thorough stakeholder analysis, and you identify Laura and Sean. Based on your interactions and analysis, you know that both Sean and Laura are low in the pecking order and so they do not wield any significant authority or power. However, where it differs is in their interest in the project. Laura has a lot of interest, while Sean is disinterested. You decide to plot them in a Power/Interest grid to help determine how you would manage these stakeholders. Which of the following is the best approach to handle these two stakeholders?

Explanations:Both Sean and Laura do not wield a lot of power and authority. However, the differentiator seems to be their level of interest. While Sean is disinterested, Laura has a high level of interest in the project. Stakeholders who have a high level of interest but who wield insignificant authority or power should be kept informed—in this case Laura. Stakeholders who have a low level of interest and who wield insignificant authority or power should be monitored—in this case Sean.

138. You are in charge of managing a software development project that is related to simulations for driving racing cars. During Quality Assurance, a number of issues have been reported in the air tunnel modelling module. On deeper analysis, it is found that many of the issues were due to not understanding the requirements clearly, and now additional time would be expended to fix the issues identified. This is a good example of:

Explanations:The question is intended to cause a confusion between preventive and corrective action. However, the question does not state any example of any steps taken proactively, so Preventive Action is not the right answer. If we were to consider Corrective action, it is a future response to the defect repair process or the correction so that the cause of error or non-conformity will not occur again, which the above question does not state. So, this is not an example of Corrective action. The question does not state anything other than reporting defects, which is Quality Control. So, option D is not the right answer. Here, the straightforward answer is option C Defect repair.

139. Which of the following is NOT part of a quality plan?

Explanations:Quality audits are part of a manage quality process.

140. As a senior member in the executive management team, you have tasked project managers within your team to provide cost estimates for a huge project. You easily foresee the cost estimate of the project to run into millions of dollars. Along with the cost estimate, you are also expecting the Basis of estimates. What would you expect to be included in the documentation for Basis of estimates?

Explanations:The correct answer is A, which states all the necessary details to be provided as the Basis of estimates.

141. Your team has just bagged a software development project. The executive management is very pleased as this is a very prestigious project. However, you are a little worried considering the complex nature of the project. You decide to try and identify the possible risks. You get all relevant stakeholders together and conduct mammoth discussions. Together, you have come up with a number of risks. However, based on your experience, you still feel that not all the risks have been identified. You decide to set aside some budget for the risks that you have not identified but are sure you will encounter. Where does this budget come from?

Explanations:The type of risk here is an unknown risk. For known risks, risk responses can be proactively planned for. For the known risks, where we cannot plan proactively, we set aside a reserve called Contingency Reserves. For unknown risks, we set aside a Management Reserve. Cost management Plan deals with how you will manage costs on your project, and Cost baseline is the baselined cost expected to be expended on the project.

142. You have been assigned to manage a project that deals with setting up a railway line connecting two cities. The project is complex with a lot of contracting involved. You and experts in your organization are evaluating if the rail line alignment machinery should be purchased outright or if it would be better to lease. The cost of leasing the equipment is $1200 per day, while the cost of an outright purchase is $96000 and a daily cost of $200. The duration of laying out the railway lines is scheduled to be an activity duration of 150 days. Should you purchase the machinery or lease it? Which option would be more economical?

Explanations:The question is looking for a simple mathematical formula. Do not get flustered by all the numbers. The activity duration is 150 Days. So, cost of leasing is 150 * 1200 = 180000, while cost of an outright purchase is 96000 + 200 * 150 = 96000 + 30000 = 126000 USD. So, definitely leasing is not cheaper and purchasing the machinery is the better option. Now which is the breakeven point of a purchase? On the 96th day of usage of the machinery, the cost of purchase incurred is 115200 $, which is exactly the cost incurred if it were leased. So, 96th day is the breakeven point and hence the correct answer is option C. Take a breather; relax and digest the details. They are not as hard as they look.

143. An activity has an Early Start (ES) of 5 days and Late Start (LS) of 16 days. What is the activity's float?

Explanations:Activity float = Late Start - Early Start = 16-5 = 11 days

144. Which of the following statements is NOT true regarding WBS?

Explanations:WBS does not help identify dependencies.

145. You are in charge of a project that is running behind schedule. Your lead architect approaches you and indicates that should introduce a change so that the project could possibly catch up on lost time. What should be the first thing you should do?

Explanations:Both options of refusing to make the change outright or making the change immediately without analyzing are incorrect, so clearly options A and D are not the right choices. The question asks about what you should do first; so though writing a change request and getting an approval is logical, even better is to first ascertain the impact of the change. You already know that the change can reduce the schedule, but you should also find the impact of this change on your other constraints, which are scope and cost. Once you have analyzed the impact of this change, you can submit a change request and seek approval. Hence, option B is the BEST course of action.

146. You are in a very happy state today as you have completed all the deliverables. This was a complex project involving a lot of challenges, but with good management and a motivated team, things have been completed successfully. What should you do next as a project manager?

Explanations:The question is looking for details related to the closing process group. Scope verification is performed during the monitoring and controlling process group. So is the case with Perform Quality Control. One of the most important things to do during project closure is to create the lessons learned prior to disbanding the team.

147. Your company has won a prestigious project that deals with building software to be used on spaceships landing on the moon. After building the schedule network diagram, you identify the critical path and also a number of near-critical paths. What does this mean with respect to Risks related to Project Schedule?

Explanations:Greater the number of near-critical paths, greater the risk of the project not meeting its scheduled completion dates. This is because the near-critical path activities will have very little float, so thereby hardly any flexibility. Any slippages in these tasks, in addition to tasks on the Critical Path, can lead to schedule slippage. Hence, options B, C, and D are incorrect.

148. You and your team have just created a schedule network diagram. You have come up with the estimates and have defined the durations and subsequently have identified the Critical Path. You now decide to do a Forward Pass" through the Schedule Network Diagram. What would you be calculating?"

Explanations:Options C and D are incorrect as the Forward Pass is not used to calculate the duration. In fact, the critical path is calculated based on duration. Option B talks about Late Start and Late Finish, which are calculated using Backward Pass. Using Forward Pass

149. You and your team have done extensive brainstorming and discussions. You have also looked up the Organizational process assets and have come up with an exhaustive list of risks. You and your team members feel fairly confident now that you know all the risks. You decide to prioritize the risks and only focus on the high-priority ones. A team member indicates that a large number of risks have very low priority. She suggests you simply ignore them. You disagree and decide to maintain a list of such low-priority risks. Where will you maintain these low-priority risks?

Explanations:The risks have been identified in the Risk register. Based on prioritization, risk priorities are also updated in the risk register. All risks that are deemed low on priority, though maintained in the Risk Register, are maintained in the Watch List specifically. The Risk Management Plan and the Issue Log are not meant to note or log risks. So, the correct answer is Watch List.

150. Which of following statements is false regarding the project scope statement?

Explanations:All the options except option D are true regarding the project scope statement. The milestones are not defined in the Project Scope Statement

151. A software development project has been awarded to one of the many vendors. Your company and the vendor have agreed to build this project using the Waterfall Methodology. You decide to check with the progress regarding when development will start. The vendor informs you that the actual development can only start after the completion of design. Which type of relationship best describes the dependency between design and actual development?

Explanations:Finish-to-Start means that the Successor Activity cannot start without the Predecessor activity being completed. In this case, the Design is the Predecessor activity and Development is the Successor Activity. So, here Development (Successor Activity) cannot start without completion of Design (Predecessor Activity).

152. Your friend, Joe, who works as a project manager in a pharmaceutical company meets you over dinner. You see a drastic change in his temperament compared with when you last met him. He seems dejected and complains that in his present organization, as a project manager, he has almost no authority and hardly any decision-making ability. Which kind of organizational structure does your friend work in?

Explanations:Your friend works in a Functional Organizational Structure. In such an organizational structure, all the power and authority reside with the Functional Manager. Such organizations are hierarchical in nature, where each employee has one clear superior. People are grouped by specialties (Functional) such as Mechanical, Accounts, Marketing, etc. These departments work independently of each other. So, the correct answer is option B - Functional Organization.

153. Which of the following uses a weighted average duration estimate to calculate duration?

Explanations:Program Evaluation and Review Technique (PERT) uses a weighted average duration estimate to calculate duration. It uses the probability of an estimate's accuracy. Expected Time = (Low + 4*Medium + High) / 6

154. Which type of relationship is often used in Precedence Diagramming Method (PDM)?

Explanations:In Finish-to-Start relationship, Successor Activity cannot happen till Predecessor Activity is completed.

155. You are managing a project related to building a skyscraper. However, as per regulations, no work can be started till the government body has approved and provided necessary clearance. What kind of dependency is this is an example of?

Explanations:This is an externally imposed or mandated dependency. Options A and B are the same and are not the correct choices.

156. What are the primary benefits of meeting Quality Requirements? (Choose all that apply.)

Explanations:All the details stated are benefits of meeting Quality Requirements. By doing a cost benefit analysis of each quality activity, we can compare the cost of Quality with expected benefit. Options B, C, and D are, in fact, results of poor Quality.

157. Which of the following statements is TRUE regarding Fixed Price Contract?

Explanations:Did you choose option D? If so, read again. Which options sound incorrect? Changes to scope cannot be made without a cost implication. In fact, this is best applicable when the seller clearly defines the scope. If work needs to begin right away, the contract type should be Time and Money, not Fixed price since you may not have everything clearly defined.

158. What are Control charts used for?

Explanations:Control charts are graphic displays of the results over a time of a process. They are used to determine if the process is in control.""

159. You are managing a project that is responsible for setting up an alcohol distillery. Your team is in its eighth month of execution. One of the vendors informs you that the agitators' delivery is going to be delayed by a week. You look up the project management plan and the schedule baselines and decide to set up all the reactors first. By moving tasks around based on your analysis, you see that there would be no impact on any of the performance measurement baselines. What should you do next?

Explanations:Be careful and read carefully regarding the situation you are being asked to evaluate. In this case, the change is not going to impact any of the baselines. In such cases, the project manager has the authority to make changes to the project if there is no impact on the baselines. This is one condition where changes can be made without undergoing change control, but note that this is done after ensuring that there is no impact on the baselines.

160. Which of the following statements is true regarding Control Account?

Explanations:Control Accounts are used to provide a cost estimate at a level higher than the work package. They are used as a technique in activity definition process. They are not used to control costs of the project and neither in Integrated change control.

161. Given a project which reports a CPI less than 1, you have asked one of your managers to generate the TCPI. Which formula should the project manager use in this case?

Explanations:The correct answer is Option B. Option A is to be used when the project is within budget. In this case, the CPI value is less than 1, so the project is not within budget. Option B is to be used when the project is over budget, which is the case here. So, it is the correct formula to use. Options C and D are not TCPI formulas. They are the CPI and SPI calculations and thus are not the correct choice.

162. In which process is meeting" not used as a Tool and Technique?"

Explanations:Meeting" is not used as a tool and technique in conduct procurement process."

163. While planning for a project, you decide to keep a good grip over project risks. You and your team members have come up with the list of possible risks and would now like to prioritize them based on their probability and impact. In which process would this activity take place?

Explanations:After the Risks are identified, risk prioritization based on impact and probability is done in the Qualitative Risk Analysis. The question states that the risks are already identified, so Risk Identification is already done. Risk Register is an output of the Risk Identification process; there is no such process as Risk Register. Quantitative Risk Analysis deals with assigning a numerical value to each risk, so the correct answer is Qualitative Risk Analysis.

164. Which hierarchical chart shows all the tasks in a list?

Explanations:Work Breakdown Structure shows all the tasks.

165. Which of the following is NOT part of the Control Quality process?

Explanations:Quality audits are part of the Perform Quality Assurance process.

166. You have a team of project managers reporting to you. Recently a new manager who is relatively inexperienced has joined your team. Considering his level of experience, you assign him to a small project. Considering low complexity and few stakeholders involved, you envision the project to have no surprises or hiccups. You have identified the number of communication channels to be only 6. However, with increase in scope of work, two additional stakeholders who need to be communicated with join the team. You ask the manager to identify the number of communication channels now. The correct answer is:

Explanations:The correct answer is 15. Note that the question provides the initial number of communication channels as 6. This means the number of stakeholders are 4. With the addition of two more stakeholders, the number of stakeholders would increase to 6. So, the number of communication channels would be 15.

167. You are managing a project that is in its first month of execution. In one of the meetings, the key stakeholder asks for some changes to be made in the ongoing work. The stakeholder is asking for the changes to be implemented immediately. You realize that the changes being asked for will need the Project Management Plan and the Scope baseline, which have already been baselined, to be updated. As a Project manager, which is the best course of action?

Explanations:Any changes being asked for or requested to any approved plan need to be formally reviewed by the Change Control Board. Option A is not the correct answer as no changes should be made without a formal approval from CCB. Option B sounds like the best choice, but the question states the impact of the change on the scope, and so the analysis of impact analysis on triple constraints

168. Comparing target dates with the actual or forecast start and finish dates is called:

Explanations:Variance Analysis: Comparing target dates with the actual or forecast start and finish dates.

169. You are in charge of a large software development project. As a part of the project schedule, it was planned to complete two core components by the end of October. You are now in August, and you realize that the project is falling behind schedule. You do a quick review and decide that the schedule can be met by adding additional staff to the activities on the critical path. This is an example of:

Explanations:As the project is falling behind schedule and deliveries cannot be impacted, the manager has chosen to add additional resources to activities on the critical path. This is an example of Crashing. NOTE that crashing may result in increased risk and rework.

170. You are in the process of determining how long it would take to complete your project. What would be the best tool to use in this case?

Explanations:A Network Diagram is the best choice to identify the Activity Duration.

171. A project is over budget when:

Explanations:CPI = EV/AC. If the EV is less than AC, then CPI less than 1, which means the project is over budget.

172. You and your team have worked hard and successfully delivered a project. The customer is happy with the deliverables, and overall everyone is happy with how the project was delivered. You have written up the performance reviews of each individual in the project team. As a Project Manager, you know that the team will get disbanded and in the next project, you may not get the same team members who so successfully delivered the current project. What kind of Organization Structure does this represent?

Explanations:This represents a Projectized Organization structure. In a Projectized organization, teams are disbanded at the end of the project. In a Functional organization, teams report to the Functional manager and are never disbanded. They continue in their own departments and continue to report to the Functional Manager. A weak matrix organization is very similar to a Functional Organization, and role of Project Manager is limited. In a balanced matrix organization, staff reports to a Project manager and a Functional Manager. In the question, there is no mention of a functional manager, so Balanced Matrix is also not the correct option.

173. The process of communicating and working with the stakeholders to meet their expectations, address issues, and foster appropriate stakeholder engagement in project activities throughout the project lifecycle is called ____________.

Explanations:The process of communicating and working with the stakeholders to meet their expectations, address issues, and foster appropriate stakeholder engagement in project activities throughout the project lifecycle is called Manage Stakeholder Engagement.

174. Choose the true statement regarding Management Reserves and Contingency Reserves

Explanations:The correct answer is D - none of the above. Contingency Reserves are part of cost baseline, while Management reserves are not. So, Option A is clearly incorrect. Contingency Reserves are meant to take care of risk-mitigating cost for identified risks. They are the costs of known unknowns, while Management reserve is for unknown unknowns—things like unforeseen work that is part of the scope. Options B and C state exactly the opposite, so they are not the correct answers, which leaves us with D - None of the above.

175. You are managing a project that is scheduled to run for an entire year. Things were looking good after the first two months. However, due to some mistakes made by the construction crew at the end of the third month, you realize that the expected work to be completed at this stage is not complete. As a result, the project is behind schedule and is also over budget. However, there are stiff penalties in the contract if the project is not complete within the stipulated timelines. Your senior management as a result has committed to additional staff to the project if required. What would be the Estimate at Completion for this project?

Explanations:Option A is to be used if past CPI is expected to continue. Option B is to be used if future work is going to be performed at the planned rate. Option C is to be used if deadlines must be met and both CPI and SPI influence remaining work. Here, the project must be completed within stipulated timelines. Option D is to be used when the initial plan is no longer valid, which is not the case here.

176. One of your project managers, Mary, reports that her project has hit a roadblock. You are surprised since just the previous week, on reviewing the project, everything seemed to be on track. She explains that a team member has identified a problem that was never envisioned in the risk identification process. Based on the analysis, the impact would be on the cost to rectify the issue. What would be the best course of action?

Explanations:The best course of immediate action on identifying a risk is to add it to the risk register along with its probability and impact. That is applicable for risks and not issues. In this case, the risk has already occurred. It is no longer a risk; it’s a reality, an issue. While scheduling a meeting is an option, it’s not the best choice. Being a project manager, you are empowered and calling up meetings every time you run into issues would not be looked upon favorably. The correct answer is using the management reserve which is meant for unknown risks. Contingency reserves are meant to be used for known risks.

177. Of the following baselines, which is not a part of the Project Management Plan?

Explanations:The project management plan contains the following baselines: Scope, Schedule, and Cost. In fact, there is no such baseline as a Quality Baseline.

178. A company wants to hire a PMP, and you are applying for the position in the company. You are scheduled to take the PMP exam in a few days. At your interview, a comment is made implying that you are PMP certified. What do you do?

Explanations:You have the responsibility to provide accurate, truthful representations concerning your qualifications, experience, and performance of services to a company.

179. A project is reporting a negative Cost Variance. What does this mean?

Explanations:CV = (EV - AC). So, if the Cost Variance is in the negative, the Actual Cost is greater than the earned value, which means the project is running over budget.

180. Which of the following is not a Risk Identification tool or technique?

Explanations:Documentation reviews help identify risks based on the plans and assumptions, so this is a Risk Identification tool. Brainstorming deals with getting together various stakeholders and identifying potential risks. Interviewing experienced project participants, stakeholders, and subject matter experts is also a great way of identifying risks. Risk Register is not a tool; it is the document in which identified risks are documented. The Risk Register is not a Risk Identification tool.

181. As a project manager of a large product, you and your team have shipped the deliverables to your customer. However, the customer has reported a number of serious issues in the quality of deliverables. As a result of this, the cost of quality of your project is deemed high. In the above scenario, which type of cost would have caused the cost of quality to increase?

Explanations:Options A, B, and C are benefits of meeting Quality Requirements. The question states what has contributed to increased cost of Quality. As the stakeholder is not satisfied with the deliverables, there is rework involved. There is an impact on productivity and increase in cost. It also decreases stakeholder satisfaction. So, amongst the choices, option D is the correct option.

182. Project Quality Management includes:

Explanations:Project Quality Management includes Customer satisfaction, Prevention over inspection, Continuous improvement and Management responsibility.

183. A relatively new project manager, Linda, joins your company. You have assigned her to a project that deals with laying out of electrical cables. One day, she informs you that some government body has been sending her a lot of queries related to the project and its layout. It seems that she did not consider the government body a stakeholder. You decide to review the list of identified Stakeholders, so you ask her to provide you with the comprehensive list. Where will this information be found?

Explanations:Stakeholder register contains details of stakeholders, such as name, location, etc. and their expectations, interests, and influence. It also provides information as to whether they are internal or external, supportive or in resistance, or neutral. So, the best source of information regarding stakeholders is the Stakeholder Register, which is option D.

184. A project is in execution. A team member, Jennifer, approaches the project manager and indicates that she is not sure of what work she needs to perform. Which document would be the best source of this information?

Explanations:WBS Dictionary provides details of the work to be done.

185. Which of the following is not a part of procurement documentation?

Explanations:Independent cost estimate is not part of procurement documentation. It is produced as benchmark to compare the seller prices. The aspects of procurement documentation are listed under table 12-1 of PMBOK.

186. You have a large complex project to deliver, and you are evaluating different motivational strategies to motivate your team to get the job done. You subscribe to the belief that to get things done and to motivate staff, they must be rewarded with monetary rewards. You believe that by rewarding employees they would get motivated. Which of the following motivational theories are you applying?

Explanations:Herzberg's hygiene theory states that it is the job content that motivates staff. So in this case, Option A is not the correct answer. Maslow’s theory of hierarchy of needs indicates the levels of needs starting with Physiological needs and ending with Self-Actualization, so Option B is not correct as well. Vroom's Expectancy theory states that employees can be motivated by altering the person's effort-to-performance expectancy, performance-to-reward expectancy, and reward valences. So, Option C is correct. Option D is clearly incorrect as the question does not indicate any imposed mandates or threats which would fall under Theory X style of management.

187. Which of the following is NOT true regarding starting a project without a formal approved project charter?

Explanations:Options A, C, and D correctly state the disadvantages of starting a project without a formal approved charter. These are the very reasons why a project should not be started without an approved charter. The correct answer to the question is option B since it incorrectly states that there is no risk of increased changes without an approved project charter.

188. A project is ahead of schedule when:

Explanations:SPI = EV / PV. If the EV is greater than PV, then SPI > 1, which means the project is ahead of schedule.

189. You are in charge of a software project, and you are almost 40% complete. The project stakeholders want a performance report till date. You had planned to use Earned Value Management methodology. You come up with the following numbers: EV = 300 AC = 100 PV = 150 BAC = 600 ETC 300. You and your team are very confident of continuing at the same rate as till now. The project has not faced any major issues and you and your team's confidence level is high that the project would complete without any hiccups. Based on this information, what would be the EAC for the project?

Explanations:The correct answer is B. The question states that issues or lack of them experienced in the project are expected to continue. So here, the past performance is expected to continue. So, the formula: EAC = BAC / CPI. CPI = EV / AC = 300 / 100 = 3 EAC = 600 / 3 = 200.

190. As a project manager, you understand the importance of identifying all relevant stakeholders, their interest and influence, and their needs and expectations. You have been assigned to handle a large construction project. You decide to do a thorough stakeholder analysis, and you identify Bob and Kelly. Based on your interactions and analysis, you know that Bob wields a lot of authority and also has a huge interest in the project. Kelly too wields a lot of power but is largely uninterested. You decide to plot them in a Power/Interest grid to help determine how you would manage these stakeholders. Which of the following is the best approach to handle these two stakeholders?

Explanations:Both Bob and Kelly have power and authority. However the differentiator seems to be their level of interest. While Kelly is disinterested, Bob has a high level of interest in the project. Stakeholders who have a high level of interest and who wield a lot of authority or power should be Managed closely, in this case Bob. Stakeholders who have a low level of interest but who wield a lot of authority or power should be Kept satisfied, in this case Kelly.

191. Regarding Rolling Wave Planning, which of the following statements are true? (Choose all that apply.)

Explanations:Option A is the correct answer. It correctly explains Rolling Wave Planning. Option B, C, and D are clearly not correct since not all details are estimated upfront, rather only the immediate activities or tasks are estimated upfront. This process is performed iteratively and not only once.

192. In your current organization, from managing projects, you have graduated to portfolio management and have a number of project managers reporting to you. Your company has bagged a prestigious project, which is very similar to the one you had executed some years ago. You ask the current project manager to look up the lessons learned for the past project. Where would these be stored?

Explanations:While all the options seem to be good choices, the best choice in this case would be Organizational Process Assets. Lessons learned are always a part of the Organizational process assets. It is such assets that enable an organization take informed decisions.

193. Your company has just bagged a project for electric cable layout and routing for a large shopping complex, and you have been tasked with providing the cost estimates. You choose to rely on your past experience of similar such projects. You breakdown the costs of the cables per foot and unit cost of cable trays. What type of cost estimating technique are you relying on?

Explanations:Parametric estimates is the correct choice. This is so because we have derived the cost per unit, cost of cables per feet, etc. Based on the unit cost, parametric estimates are used to determine an estimate of the total cost.

194. When does Scope Verification occur?

Explanations:Scope Verification occurs at the end of each phase of the project. Option A relates to Product verification not Scope verification.

195. Which of the following statements is NOT true regarding differences between administrative closure and contract closure?

Explanations:All the options except Option D correctly state the differences between administrative and contract closure. Option D is not true since in both forms of closure, lessons learned are documented and updated to the Organizational Process Assets (OPA).

196. You are responsible for managing a project that deals with laying out a freeway connecting two major port cities. Progress in the past has been smooth, but lately in the past few months, you have observed a schedule and budget overrun. You decide to hold a meeting with your team members. On discussions, you realize team members went ahead and made changes at the behest of the client requests on site. You are pretty sure the changes were not a part of the project scope statement. This is an example of:

Explanations:This is an example of Scope Creep. Integrated change control deals with formally approving or rejecting changes before they are implemented, so it is not the correct answer. Fast tracking is a schedule compression technique, so it too is not the correct answer. While Gold Plating is related to change in scope it is generally done intentionally or knowingly for some strategic purpose. Scope creep relates to uncontrolled changes in product or projects scope and is often due to client interference.

197. You are part of a Quality Assurance team and have scheduled a Quality Audit for one of the projects. What would not be a goal or objective of performing this audit?

Explanations:Option A, B, and C are the objectives or goals of this exercise. The purpose of the audit is to identify what is working well and what is missing, but never to find root cause of issues, which is done in Process analysis. Since the question is asking what is not a goal or objective of performing a Quality Audit, option D is the correct answer.

198. As per Maslow’s theory of Hierarchy of needs, which is the correct order of needs?

Explanations:Option D is the correct answer. As per Maslow’s theory of Hierarchical needs, the first need of humans is a basic need for survival (air, water, food, etc.). This need is termed Physiological. Once this need is met, the next need is the need of Safety and Security. This can be in the form of a Secure Job, Health, Insurance, etc. The next need is termed need of Love or Belonging. As per Maslow’s theory, humans need to belong and find acceptance among their social groups. The fourth need is termed the need of Esteem—to be respected and valued by others. Once the above four needs are met, then the final one is Self-Actualization, which is the desire to accomplish. So, the correct order of needs as per this theory is Physiological, Safety, Love/Belonging, Esteem, and Self-actualization.

199. You have just completed developing the Schedule Network Diagram for a project that deals with building supersonic state-of-the-art Jet planes. You have identified your critical path which includes building a wind tunnel. You see that in addition there is another path which deals with building the tail of the plane, whose duration is close to the critical path. You also notice considerable floats on the other paths. You now need to assign resources to the tasks. You have a few team members who are highly skilled and a team of resources who are relatively inexperienced. What would be the best course of action while assigning resources?

Explanations:Options A and C are wrong. You should always ensure activities on the critical path do not get delayed. So, having the best equipped staff on critical path activities is important. Option B cannot be the BEST choice. If you assign all the experienced staff on building the wind tunnel, the critical path activities are taken care of but the question also states of a path which is near-critical—building of the tail. Not paying attention to this path by assigning inexperienced staff is not a good option. Among the choices, option D is the best fit, where you are paying attention to both the critical path and near-critical path by assigning your best and most skilled or experienced resources to the activities on both paths.

200. Which of the following determines if a project idea is realistic?

Explanations:Feasibility study determines if a project is realistic or not.